This from Save Porty Park fb page
The option appraisal commissioned by the council in 2006, ruling out most of the alternative sites contained some serious errors and inconsistencies. Prior to the planning application for Portobello Park, msp Kenny MacAskill asked council colleagues to review the process, but they refused to do so.
Our concern is that the appraisal was carried out with a predetermined outcome. The council had alre
ady cleared stated that the plan was to build on Porty Park. They even produced glossy promotional leaflets detailing their plan. The feasibility study was constructed to support that outcome.
Let's hope they don't make the same mistake again. The option appraisal must be open minded, factually accurate and challenging. New and imaginative solutions should be sought. There is no point just rehashing the previous one.